Business Center Drive

Location:

Business Center Drive

Estimated Completion Date

July 2011

Project Details

Two lanes of Business Center Drive already exist from Broadway to the southern Pearland Town Center entrance. The limits of the this project include the remaining two lanes from Broadway to the southern entry of the Pearland Town Center and four lanes from the southern Pearland Town Center entrance to CR59. The proposed cross section is concrete curb and gutter with sidewalks. The project will also include improvements to CR59 that will accomodate the increase in traffic.

Project Justification

This project will provide a secondary thorough fare to alleviate traffic near the Pearland Town Center.

More Information

For current detail information on this project, please visit our monthly updates